Showing posts with label Foundation. Show all posts
Showing posts with label Foundation. Show all posts

Tuesday, October 28, 2014

What is Pile cut-off Level? Pile Foundation

Pile Cut-off level is the actual level at which the piles below pier are made to be of the same level. The concrete of pile is cut-off at the specified level (given in the specifications or drawings usually around 75 mm) while the steel is kept projected in-to the pile cap to make an effective bond between pile cap and piles.

What is Pile Cut-off Level

Why pile is trimmed or cut?


For Piles casted in dry bore holes while using temporary casing, piles heads shall be casted to a level a bit above the specified cut-off so that, after cutting or timming, a sound concrete connection can be made with the pile.

While we cast the piles under water we use tremie method of concreting. In this method the shaft of concrete pile is casted by using a tremie pipe which is lowered below the water level or the interfacing concrete and concrete is poured with pressure while the slurry and other raw concrete or weak concrete comes up. For tremie method slump mix should be greater than 175 mm.

Pile cut-off level can be above or below the group. When it is above ground, Concrete should overflow from the pile head on completion. Due to tremie method the upper part of pile consists of weak concrete as well as some contaminated boring debris.

In case the pile cut-off below the ground, the concrete level should be raised to allow for around 1 m for trimming off the weak concrete.

Traditionally the cropping or trimming process to achieve the required cut off level is done using a jackhammer or hand-arm vibration syndrome (HAVS).

Monday, January 13, 2014

What are the different types of shear failure in foundation?


Soil mostly fail in shear, thus when foundation load is transferred to the soil, the soil may fail in shear in 3 modes names as; (a) General Shear Failure (b) Local Shear failure (c) Punching shear failure;
The type of failure that will occur in the soil due to foundation load will depend upon the type of soil, its state of compactness or gradation in case of granular soil;
Failure Types in foundation


a)    General Shear Failure;

The most common type of failure in foundation is general shear failure; general shear failure mostly occurs in dense or very dense granular soil which might be sand or gravels or it may be stiff or hard cohesive soil which is well compacted or having low moisture content. In load deformation curve there is relatively small deformation with increasing load showing a clear peak represented by a sudden drop of load after peak.
In the failure of the soil mass the failure plane will extend to the surface of the soil and there is clear bulging extending out of the soil surface. In case of soil sample the failure will occur at peak load and the failure planes will move relative to each other.

(b) Local Shear Failure

 Local shear failure mostly occur in loose and medium dense granular soil which might be sand or gravel and soft and medium cohesive soil which might be medium compacted or high moisture content.
In load deformation curve; there is no peak and after a certain load there are sudden jerks, in the soil mass there is small broken bulging and the failure surface is not that clear. Same is the case will the soil sample failed in local shear failure while testing with triaxial or unconfined compression test.

(c) Punching Shear Failure:

Punching shear failure occurs in soil which is very loose granular or very soft cohesive soil. The settlement in foundation is considerable with increasing the load and load deformation curve is very steep. In soil mass the failure surface will not extent to the ground surface.
 The test sample may not be handled or may slump when taken out of the sampler.

Keywords for this post

foundation engineering, types of failures of foundation, failure types of foundation, general shear failures, shear failure in soil, types of shear failure, foundation failure types.

What is Foundation Engineering? Course content, books, solved asigments, quizzes

Foundation Engineering is a very interesting and use full subject in terms of applicability and scope in civil engineering. Importance of Foundation engineers can be understood easily by considering the importance of foundation in a structure. This post is about the introduction of foundation engineering, course contents, assignments and books which are mostly referred in foundation engineering.
Foundation Engineering


Foundation engineering is a field of civil engineering related to the analysis and design of shallow and deep foundation, along with testing of the soil and its geo-technical foundation, creating a soil profile, selecting a suitable barrow pit if needed, enhancing the bearing capacity of soil by various methods, stabilizing the soil if needed, avoiding the land-slides and other ground failures.

After studying foundation engineering you would be able to analyze the load carrying capacity of a foundation, design of shallow foundation which means selecting the suitable depth and dimensions of the footing by considering the geo-tech properties of the soil, design of pile foundation, selecting the depth and calculating the spacing within a group of piles, determining the efficiency of group of pile foundation.

You will know how to evaluate the pile load test data, draw graphs of it, how to conduct the Standard Penetration Test and understanding the test results, understanding the Cone Penetration test and how to use its properties in developing the foundation of a structure, similarly how to conduct vane shear test and using its properties find out the cohesion of the soil and using this test result design the foundation for that soil.

Course Contents

Review of Soil Mechanics and Geo-technical Engineering
Factors to be considered in foundation design
Geo-technical Design of Shallow foundation
Introduction and design of deep foundation

Assignment

Report on any mega structure by considering the geo-tech investigation and consideration in that project
Design 1; Design of Shallow foundation based on Standard Penetration Test (SPT)
Design 2: Design of Shallow Foundation based on results of Cone Penetration Test (CPT)
Design 3: Design of Shallow Foundation based on results of Field Vane Shear Test
Design 4: Design of Deep foundation and pile foundation and testing by pile load test
Collection of Graphs from various topics of soil mechanics
MCQs from various topics of shallow foundation and deep foundation

Lab Portion:

General Soil Properties Problems
Bearing Capacity of shallow foundation problems
Field Vane Shear Test

Books Referred

1    Soil Mechanics & Foundation Engineering    (4th Edition) Prof. V.N.S Murthy
2    Foundation Analysis and Design    (5th Edition)  by Joseph E. Bowles
3    Principles of Foundation Engineering    (6th Edition)    Braja M. Das
4    Fundamentals of Soil Mechanics        Siddique Quereshi                  & Aziz Akbar
5    Foundation Design and Construction    (5th Edition)  M.J.Tomlinson
6    Soil and Foundation    (4th Edition) Chery, Liu and Jack B. Evett
7    Soil Mechanics & Foundation Engineering B.K Ramiah, L.S. Chickanagappa

Quizzes

Quiz # 1; from a video lecture about soil investigation
Quiz # 2: From SPT, CPT, VST

Download the package:

This package has been designed to ensure that maximum of the above course will be provided; including books, notes, class notes, lectures, assignment solution and everything.
To download Click the Button below;
 

Tuesday, January 7, 2014

51+ MCQs of Geo-Technical and Foundation Engineering you must know

Foundation and geo-technical engineering is a very interesting and useful field of civil engineering. Like the name of the subject it plays a pivotal role in the success or failure of any structure. The portion upon which the load of building or super-structure rests is called a foundation and the lower part of the foundation is footing. The ultimate destiny of any load in the structure is the underneath supporting soil and the mean which we adopt for this transfer is footing.

Geo-technical and foundation engineering MCQS


 Why foundation is necessary? Well a common question but very simple answer could be, how will you stand if you don’t have feet? Obviously you will not be able to stand on your own load, thus to stand the loads of the building along with the live load of persons, machinery etc, footing is needed secondly if we place the column or wall directly over the footing the wall or column will sink easily due to high contact pressure.

Contact pressure is decreased by increasing surface area and this is where the footing plays its role to distribute the load over a larger or wider area. Here is this post I will not be discussing about the whole subject of course because it is out of the scope of the post, below are simple, useful and important questions along with answers which all geo-tech and civil engineers must know;


In SPT, The test uses a thick-walled sample tube, with an outside diameter
A    45 mm
B    50 mm
C    55 mm
D    53 mm
Correct Choice    □ B


2) In SPT, we terminate the test for no of blows which are obtained to drive the required 12-in
    A    70 blows
    B    80 blows
    C    90 blows
    D    100blows
Correct Choice    □ D


3) Gravels are ……………. Lines more previous than clays
    A    10, 000
    B    50, 000
    C    1 million
    D    30,000
Correct Choice    □ C


4)     The design of  ……………………………………………… dams vary much based upon the permeability of soils used:
    A    Concrete dam
    B    Earth Dam
    C    Coffee Dam
    D    Steel Dam
Correct Choice    □ B


5) Units for K (co-efficient of  permeability ) are :
    A        m^3/sec
    B        〖cm〗^2/sec 
    C        m/〖sec〗^2
    D       cm/sec
Correct Choice    □ D


6) Major principle stress is given by  ð1 = 40 KN/m^2   and Minor principle stress is given by ð3 = 20 KN/m^2  , share strength is givin by :
Z = (ð1-ð3)/2
    A    20 KN/m^2
    B    40 KN/m^2
    C    60 KN/m^2
    D    10 KN/m^2
Correct Choice    □ D


7)Unconfined compressive strength is given by 120 KN/m^2  , what  will be the unconfined shear strength or cohesion?
                    C=qu/2                                            
    A    60  KN/m^2
    B    80  KN/m^2
    C    99  KN/( m^2 )
    D    120 KN/m^2
Correct Choice    □ A


8) According to ASTM D2573, in Field Vane Shear test with the vane in position, apply the torque to the vane at a rate which should not exceed ______.
A    1 °/sec
B    4° /sec
C    1 °/min
D    4 °/min
Correct Choice    □ A


9) According to ASTM D2573, Field Vane Shear test in case of very soft clays the time to failure may be as much as ________.
    A    3 – 5 min
    B    5 – 8 min
    C    10 – 15 min
    D    15 – 18 min
Correct Choice    □ C


10) A structure is erected on impervious clay whose thickness is 12m. Drainage is possible both at upper and lower surfaces. Coefficient of consolidation is 0.015 cm2 per minute.For attaining 50% consolidation with a time factor of 0.20, the number of days required??
    A    3123
    B    3333
    C    3233
    D    3313
Correct Choice    □ B


11) A Standard proctor compaction test performed on sample of crushed limestone(Gs=2.70) obtained a maximum dry unit weight of 90 Pcf at OMC.A field compacted sample showed a moisture of 28% and unit weight of 103.7 pcf.Find the relative compaction (RC)=?
    A    70%
    B    80%
    C    90%
    D    100%
Correct Choice    □ C


12)The moist unit weight of a soils is 16.5 KN/m3.Given that the w=15% and Gs=2.70 , Find the porocity n=?
    A    46%
    B    48%
    C    50%
    D    52%
Correct Choice    □ A


13)Number of blows N=32, Find allowable bearing capacity in KPa =? using B<4 by="" ft="" method.="" meyerhof="" p="" s="">
    A    14
    B    12
    C    10
    D    8
Correct Choice    □ D


14) The permissible settlement of a shallow foundation  on a rock evaluation of safe bearing pressure from a plate load test is taken as ………………
    A    12mm
    B    25mm
    C    40mm
    D    50mm
Correct Choice    □ D


15) In loose coarse gravel, the split spoon (SPT)  tends to slide into the ………………. and ………………..resistance is observed.
    A    large voids, low penetration                        
    B    small voids, large penetration
    C    small voids, small penetration                     
    D    large voids, large penetration
Correct Choice    □ A


16)Expression for  “Q allowable” using Mehyerhoff s equation  in FPS system for B< 4ft  is
    A    N/4 Kd                                               
    B    N/2.5 Kd
    C    N/8 Kd
    D    12NKd
Correct Choice    □A


17)The contact pressure of flexible footing on non-cohesive soils is:
    A    Uniform throughout.
    B    More in the centre than at edges.
    C    Less at the centre than at edges.
    D    Not on the footing.
Correct Choice    □ B


18)In case of lateral loads or moments, the foundation should also be checked to be safe against sliding and overturning The FOS shall not be less than
    A    1.75 against sliding
    B    2.0 against overturning.
    C    3.0 for wind seismic
    D    a,b both
Correct Choice    □D


19)For Strip Spread Footings
- Length (L) to width (B) ratio,
    A    L/B < 10
    B    L/B ≥ 10
    C    L=B
    D     B is very small
Correct Choice    □ B


20) In shallow foundation, the contribution of side shear stress is …….?
    A    Maximum
    B    Minimum
    C    Negligible
    D    Average
Correct Choice    □ C


21) Which of the following statement is correct?
    A    The settlement of rigid footing on cohesion less soil is uniform throughout.
    B    The settlement of flexible footing on cohesive soil is less in the center than at the edges.
    C    The settlement of flexible footing on cohesion less soil is more in the center than at the edges.
    D    The settlement of rigid footing on cohesive soil is uniform throughout.
Correct Choice    □A


22) In shallow foundation if Rw = 1&Rw'  = 0.5 than where the water table lies:
    A    At base of footing  
    B    Below the footing
    C    At the ground level
    D    Any where at the mid
Correct Choice    □ A


23) If Qu = Qs+ Q b where Qs = Shaft resistance,Qb = Bearing resistance
And Qs is greater than Qb the pile is classified as

    a.    skin friction pile
    b.     End bearing pile
    c.    Cast in –situ pile
    d.     Driven pile
Correct Choice    □ A 


24) Which type of pile is used near sea to protect harbor just by absorbing the effect of floating objects
    a.      Anchor piles
    b.      Fender piles
    c.     Batter piles
    d.     Sheet piles  
Correct Choice    □B


25) For over consolidated soil the value of OCR is
    a.    equal to one
    b.     greater than one
    c.    can’t be measured
    d.    smaller than one
Correct Choice    □ B


26) Find the approximately No. of Standard Penetration’s (N)  by using Cone Penetration Resistance (qc) of 20 MPa, if ‘k’ factor is 0.3 and the soil is silty sand; (qc=kN)
    A    66
    B    77
    C    88
    D    99
Correct Choice    □A


27) Max. Overburden pressure (q’) at the tip of the pile can be calculated by;
    A     2γDf
    B     (1/2)γDf
    C     γDf
    D    (3/2) γDf
Correct Choice    □C


28) If the ultimate load carrying capacity(Qu) of certain pile is 500 kips, the shaft resistance (Qs) is 415kips and bearing resistance (Qb) is 40 kips then comment about the nature of the pile;
    A    Cast in situ pile
    B    Driven Pile
    C    Sheet pile
    D    None
Correct Choice    □ B


29) If the shaft resistance Qs = 300,000 lbs  and bearing resistance Qb is equal to 30,000 lbs then ultimate load carrying capacity Qu is equal to;
     A    300 kips
    B    330 kips
    C    310 kips
    D    None
Correct Choice    □ B


30) For clayey soil “Fs” will be equal to
 “where Fs is pile unit surface skin friction”
    A αc+qk tanδ
    B qk tanδ
    C αc
    D none of above  
Correct Choice    □C


31) if a soil is fully saturated having void ratio 0.67 what wil be the porosity?

A 40%
B 42%
C 44%
D 46%
Correct Choice    □ A


32) D60 is 9.6mm,D30 is 2mm and D10 is 0.16mm what is value of Cc (coefficient of curvature)?
a)2.4
b)2.5
c)2.6
d)2.7
Correct Choice    □ C


33)  For construction of an embankment, if max dry unit wt is 120.5lb/ft3, optimum moisture content 13%, dry density 118lb/ft3, actual field moisture content 12.9%, the relative compaction will be?

A-94%

B-96%

C-98%

D-100%
Correct Choice    □ C


34)The total weight to be arranged for a pile load test in compression should be:
    A    equal to the anticipated maximum test load
    B     at least 100% greater than the anticipated maximum test load
    C     at least 50% greater than the anticipated maximum test load
    D     at least 10% greater than the anticipated maximum test load
Correct Choice    □ D


35) A plate (0.3 x 0.3 m plate size) load test performed on clayey soil gives ultimate settlement of 2.2 mm. The ultimate settlement of 2 x 2 m isolated footing will be:
    A    18.65 mm
    B     12.50 mm
    C     14.67 mm
    D    16.39 mm
Correct Choice    □C


36) Usually for driven piles, the value of lateral earth pressure co-efficient “K” is
    A    ≥1
    B    ≤1
    C    1.75
    D    zero   
Correct Choice    □ A


37) For very hard-clay ,value of cohesion reduction factor “α” is
    A    1
    B    0.3
    C    0.4
    D    3
Correct Choice    □C


38) In vane shear test if  ( 0.6 < Id < 1.8 )  than the soil type will be:
    A    Sand      
    B    Silt
    C    Clay
    D    Gravely soil
Correct Choice    □ B


39) In vane shear test initially  ΔA, ΔB (before inserting the blade) must be in the Ranges:
    A    Î”A= 15 to 30 kpa         ΔB= 15 to 80 kPa
    B       ΔA= 5 to 30 kips           ΔB= 5 to 80 kips
    C      ΔA= 5 to 30 kpa            ΔB= 5 to 80 kPa
    D      ΔA= 20 to 30 kpa         ΔB= 20 to 80 kPa
Correct Choice    □C


40) Foundation on loess in situ dry densities range from?
    A    10 to 14.6kN/m3
    B    10 to 15.5KN/m3
    C    10 to 16.5KN/m3
    D    10 to 17.5KN/m3
Correct Choice    □C


41) When footings are to be placed adjacent to an existing structure, the line from the base of the new footing to the bottom edge of the existing footing should be
    A    30 degree
    B    45 degree
    C    60 degree
    D    90 degree
Correct Choice    □ B


42) The vane head should be turned five complete rotations at a speed of approximately ________seconds per rotation, and steps 3.6 to 3.8 repeated
    A      10
    B      30
    C      60
    D      5
Correct Choice    □ A


43) The backfill used in Reinforced earth structures should contain less than _____ fines content as required by the AASHTO Specifications for Highway Bridges.
    A    15 %
    B    18%
    C    25%
    D    28%
Correct Choice    □ A


44) In CPT test, the rate at which we push the instrumented con tip into the ground is
    A    2 centimeters/second
    B     4 centimeters/second
    C     5 centimeters/second
    D     3 centimeters/second
Correct Choice    □ A


45) In Case of  SPT , the graph between Depth of influence and Breadth has behavior
    A        Inversly propertional
    B        Constant line
    C        Directly proportional
    D        Non unfiorm behviour
Correct Choice    □C


46)Geotechnical investigation of soil resulted in SPT value of N=30. If square footing dimensions are confined to be 5 feet. Suggest allowable bearing capacity for permissible settlement of 1 inch using Teng Method.
    A    6 K/ft2
    B    7 K/ft2
    C    9 K/ft2
    D    8 K/ft2
Correct Choice    □ B


47)Geotechnical investigation of soil resulted in spt value N=25, allowable bearing capacity of soil was found to be 6k/ft2. Suggest suitable dimensions of square footing using Meyerhof Method for (B>4feet)?
    A    5 feet
    B    6 feet
    C    7 feet
    D    8 feeta
Correct Choice    □A


48)Geotechnical investigation of soil resulted in SPT value of N=30. If square footing dimensions are confined to be 5 feet. Suggest allowable bearing capacity for permissible settlement of 1 inch using Teng Method.
    A    6 K/ft2
    B    7 K/ft2
    C    9 K/ft2
    D    8 K/ft2
Correct Choice    □ B


49)The un-drained shear strength  of cohesive soil and SPT N  is controlled by
    A    Plasticity
    B    Sensitivity
    C    Fissuring
    D    All of  Above
Correct Choice    □D


50)Black cotton soils are:
    A    Residual Soils
    B    Organic  Soils
    C    Expansive Soils
    D    Ash Soils
Correct Choice    □ B


51)The expansion of soil due to shear at a constant value of pressure is called…….
    A    Apparent cohesion
    B    Dilatancy
    C     true cohesion
    D    Consistency
Correct Choice    □ B


52)Inorganic clays of high plasticity and having high inherent swelling capacity have liquid limit exceeding…………. % and plastic index over …………..
    A    20%   ,    10              
    B    40%  ,  30              
    C    30%    ,    20
    D     50%  ,  30
Correct Choice    □D


53)The best way to avoid damage from expansive soils is :
    A    To give a shallow foundation
    B    To give a  pile foundation
    C    To give foundation beneath the water zone
    D    To use of cobbles
Correct Choice    □ C


54)Which of the following is deep foundation
    A    Mat foundation
    B    Strip Footing
    C    Rock Anchor
    D    Cassion
Correct Choice    □D

From Editors Desk

These simple Multiple Choice question of foundation engineering is to help civil engineers and geo-technical engineers to enhance and fresh their knowledge, if you have found any error or you want to add any question in it you can comment below or you can send me at admin@iamcivilengineer.com. 
Hope you would like it. Don't forget to share it with your friends and buddies.

Sunday, December 1, 2013

What is pile foundation? What are the Uses of different types of Piles?


A pile is a long slender foundation member, made either of timber, structural steel or concrete which might be cast-in-situ or driven and acts as a structural member to transfer the load of the structure to a required depth in deep foundations carrying a load which may be vertical or lateral or lateral plus vertical
Pile Foundation

Uses of Piles

As far as deep foundations are concerned there are no. of types of deep foundations and pile foundation is among one of them; uses of Pile Foundation depends on the type of pile used, the intended function for which the pile is used, the load which is to be applied on the pile and the type of material which is used for the construction of the pile;
The following are the uses of piles;

a)    End Bearing or Compressive Strength

Sometimes we use the piles to achieve the required compressive strength in the soft soil; in that case we use the piles to transfer the load through that soft soil to a suitable bearing stratum by using the end bearing or toe bearing property of the pile

b)    Scour Depth:

To build a structure within the water and on the water river or canal bed; we have to build the foundation through the river bed and within the scour depth. To learn more on what is scouring? What is scour depth and how to calculate scour click here.
For River Ravi in Pakistan the scour depth is 30 to 35 cm below the bed. In these sorts of situations if we go for shallow foundation we might have to use coffer dam or some diversion which is very uneconomical.

c)    Tension or Uplift:

Piles are usually used to carry compressive nature of load through tip bearing or end bearing; but in case of tall structures or like towers there might be tension that must be resisted by piles. For example for a tower carrying high power transmission lines the thrust of wind might produces over turning that must be resisted by the tension piles; other options include use of deep foundation or thick raft which is sometimes uneconomical.

d)    Vibration Control

For foundation of buildings supporting vibrating equipments like Turbines and silos etc where the vibrations is significant and might cause failures as well; there are two options there you might go for the massive block to absorb the vibrations or you can use the deep foundations and same that the massive block is very uneconomical.

e)    Compaction Piles:

Sometimes the piles are driven in a weaker strata of soil to increase the bearing capacity of the soil those piles are called compaction piles; and thus by using compaction piles we can increase the bearing capacity of the soil.

f)    Rapid Construction

To tackle or to avoid any problem relating to soils deep foundations and specially piles are a very good option when the time schedule is very tough. They are rapid to construct and not difficult to design as well.

incoming keywords:
what is pile foundation types of pile,what is pile foundation construction,what is pile foundation used for,types of pile foundation
,what is raft foundation,define pile foundation,pile cap foundation,
difference between shallow foundation and deep foundation

What is scouring, Bridge Scouring? How to calculate Scour Depth?

Scouring can be defined as a process due to which the particles of the soil or rock around the periphery of the abutment or pier of the highway bridge spanning over a water body, gets eroded and removed over a certain depth called scour depth. Scouring usually occurs when the velocity of the flowing water increases or crosses the limiting value that the soil particles can easily handle.
Scour at bridge Pier and abutment

When Scouring Happens? Causes?

Scouring can be easily observed during the flood being passed through that water body. Scouring is initiated at the nose of the piers or at the sharp bends. Estimation of scour depth is very important for the design of foundation for abutment or pier. Scouring compromises the structural integrity and thus causes failure of the structure. It has been estimated that over 60 % of the highway bridges are being collapsed due to scouring.

When the discharge within the water body passes the allowed discharge; which is usually the case when flood is there; the scour is initiated; the scour depth can easily be obtained after the flood by finding the depth of the scour in reference with the surroundings or existing structures. If this is not possible the mean depth of scour may be easily obtained by a mathematical formula for natural streams in the alluvial depth.

How to Calculate or Estimate Scour Depth?

Hydraulic Engineering Circular (HEC) has published a manual in which the methods are mentioned some of which are empirical equations or graphs to estimate the scour depth based on the discharge, flow velocity or flow depth etc.

Zeller Equation for estimation of scour depth

If the bed is sand bed streams we can use the empirical Zeller Equation for estimation of scour depth;

Ygs = Ymax [(0.0685 Vm^0.8) / (Yh^0.4 Se ^0.3)-1]
Where Ygs = general scour depth (ft), Ymax is maximum depth of flow, Vm is the average velocity of flow(ft/sec), Yh is hydraulic depth of flow (ft) and Se is the energy slope (or bed slope for uniform flow), (ft)
From actual field measuring scour depth charts to estimate scour depth;
Estimate Scour Depth


This method is applicable only for coarser sands where the bed slope ranges from 0.004 ft to 0.008 ft.
Other empirical methods are also there like Neil, Blench and Lacey for estimation of the scour depth.

Incoming Search Terms
scour depth definition,scour depth calculation,afflux,scour depth meaning,scour depth formula,scour depth calculation formula,scour depth in bridges,local scour

Tuesday, November 12, 2013

Now You can Land Airplanes in the Sea - Kansai International Airport Japan


Japan, the land of rising sun was advancing with technology at a fast rate after World War II, Its economy was on the verge of stabilization. But here the question arises where do you put a plane in a space that run out of space? The Japanese have found its answer you can make the airplane to as well as it flies. In Japan at that time the largest international airport was in Tokyo; the middle of the island. Business owners had to ship their goods hundreds of miles so they could be exported out of the country. This was both costly and time – consuming.
Osaka was the ancient capital of Japan and the former playground for the last samurai. The home of 3 millions Japanese, a new energy in Osaka has propelled this place to become the commercial and industrial center of western Japan. But in order to compete with their big sister Tokyo – Osaka needed to find a way to bring in more people with a Yen for Big business. The solution that was devised “a much bigger airport – to open up the skies”
Building an international airport in Kansai region of Japan was developed in late 1960’s, but the owners of the land and angry farmers were opposing the idea and thus the idea of the project was forced to shut down. The Kansai region included the large cities of Kobe and Osaka, advancement in these two cities forced the city designers to find a solution as to where to put an airport. The majority of land in Kansai region is being filled by the inhabitants and the only practical solution to this problem was to build it on water.

SUBSURFACE INVESTIGATION

First and foremost important step related to any geotechnical application is to gather information about the soil as much as we can. For a task the scale of Kansai, an extensive investigation was necessary to characterize the subsurface since very little was known about the soil conditions below the bay,


Fig 1 Bore Holes for Geo-tech investigation
Scientists have used large barrages and rigs, to let engineers to be able to bore deep into the seabed and gather information about the type of soil they would be resting their airport on. The findings of the geotechnical investigation was as under; the top 60 feet of the clay was soft-alluvial clay called Holocene layer which has hardness roughly equivalent to that of toy clay, this layer had loosely placed sediment. But that was not much problem for the engineers as they had much experience in building on such similar deposits off the shore of the bay and had means to control it. The problem which they had about to face was below that alluvial clay layer was old, diluvial deposit of stiff clay,  which had never been build on before.
Fig. 2 Subsurface profile of the Kansai Airport Foundation

Main Construction Process

Engineers have divided the main construction into three different stages
(i)                 Remediation of the seabed
(ii)               Placement of seawall
(iii)             fill

Sea bed remediation

The problem that was faced by geo-tech engineers here was settlement, as the underlying soil was clay. As we know that clay composed of very small soil particles having pores in them, these pores on application of load can be re-arranged for an unknown time, and more over this process of consolidation is very slow, but has a significant effect on the working of the structure.
In the case of the Kansai Airport, the upper alluvial layer was highly compressible and is impermeable as well, thus engineers have used a technique called sand draining method, approximately one million sand columns were inserted into the top layer of the bay to improve drainage conditions. This allows the water to flow horizontally to a column and then exit relatively quickly in a vertical direction because the sand has high permeability. The sand columns not only allows the water to drain quickly to avoid long term settlement but also strengthens the soil during construction.
Fig 3 : Sand Draining Technique to Increase settlement Rate of consolidating clays

Seawall

After improving the sub-surface of the bay the scientists have to fight with the high speed tides of the sea, because if these high velocity waves can’t let the inhabitants to live near the sea how can these waves allow the airplanes to live within the sea; for fighting this problem they have devised a seawall, special “tripod” blocks were used on the seaward side to disspiate the energy of any harsh waves. These 2 ton blocks slowly arose from the seabed creating a ring of concrete 40 ft above sea level.
Fig 4: typical cross-section of the seawall
Fig 5 : Complete seawall

Fill:

Once the seawall was completed, workers started on the body of the island, The source of their fill material, which consists of different grades of sand, gravel and rock, was from three nearby mountains. Trucks transported from the borrow site to the nearby ships which shipped it three miles to the site. It almost took four years to fill such a land and it took 750 million cubic feet of fill, three mountaintops had disappeared.
To tackle with the problem of settlement, the first question that was put forward to the scientists was How much the island would ultimately settle. By using their knowledge of soil mechanics they have calculated the ultimate settlement of the soil to be between 19 and 25 feet. Interestingly enough, the airport was designed for an island that would settle only 19 feet. By the time the island was completed in 1990, it had already settled 27 feet and was continuing at a rate of 2 inches per month. This prompted designers to put an extra ten feet of fill on top to compensate for the difference, adding even more stress to the seabed.
The deep clay layer was not a uniform or homogeneous layer, it has sand layers within its mass and engineers believed that these sand layers will allow the water to drain quickly themselves but care full study shows that among these continuous sand layers there are a few discontinuous sand layers which doesn’t allow the water to drain and thus there comes the problem of differential settlement.
To encounter the differential settlement between island and the terminal, engineers have lined the basement of the terminal with a quarter of a million tons of iron ore. Without iron ore, the terminal weight would be less and the remaining island would sink and settles thus the terminal might fail thus the additional weight of the iron ore beneath the terminal allows the terminal to settle at approximately the same rate as the rest of the island.
The runways were paved specifically with asphalt and not the concrete reason being that if some patch holes appears they could be paved easily with asphalt and concrete could fail in this case easily. The terminal was build on 900 columns, the height of these columns was controlled by a hydraulic jack and the settlement of these columns was computer monitored thus if some differential settlement might be observed the hydraulic jacks come in place to counter that settlement. Once the jacks were removed steel plates were slid under the columns.

Earthquakes and other Natural Disasters:

Engineers have used rocks when they were filling within the seawalls as a fill, inclusion of these rocks had some objective and that was to absorb any earthquake shaking activity and that was proved fruitful in the 1995 earthquake when after 15 years the terminal was opened an earthquake rocked the Osaka Bay area in early morning. Kansai Airport was just 18 miles from the epicenter and the officials were surprised to see the results of minimal damage to the island. With the exception of a few cracks within the sidewalks the terminal was fully in perfect condition.

References


·         Kansai International Airport Land Development Company, Kald Information Center: URL: < http://www.kald.co.jp/index-e.html>
·         Takenaka Corporation, Modification Method for Differential Settlement: URL: <http://www.takenaka.co.jp/takenaka_e/quake_e/fudo/fudo.htm>
·         The Learning Channel, “Super Structures of the World: Kansai International Airport”, Original Broadcast, 1999.
·         Kansai International Airport “Mega Structure” Series on National Geographic Channel.